Work Completed This Week - 6/21/09 • Roofing is complete at the balcony infill. • Drywall taping is in process at PACU. • Painting and ceiling grid is in process at Sterile Processing. • Demo has started at the interior portion of the balcony infill. • The fan and filter has been installed on the roof for the ED Isolation rooms.
Work Completed This Week - 6/14/09 • Metal panels at Stair S-01 penthouse are complete. • Drywall has started at PACU. • Taping has started at Sterile Supply. • Spray fireproofing was completed at the balcony infill. • MEP rough-in continued at Acute Care.
Work Completed This Week - 6/7/09 • Roofing at S-01 Penthouse is complete. • CT Scan was completed and is back in operation. • MEP continued at PACU and Sterile Processing. • The balcony infill steel was installed. • MEP continues in ED Treatment Rooms and ED Imaging.
Work Completed This Week - 5/31/09 • Penthouse construction continues at Stair S-01. • Framing at Acute Care started. • MEP continued at PACU and Sterile Processing. • The north balcony infill was prepared for steel erection. • X-ray support structure was completed in Rad 206.
Work Completed This Week - 5/24/09 • Penthouse construction started at Stair S-01. • Piping over the CT Scan room in the E.D. was completed. • Steel work at Stair S-01 continued. • Demo at Acute Care continued. • Flooring was installed at E.D. Waiting.
Work Completed This Week - 5/17/09 • Roof slab was cut open at Stair S-01. • MEP continued at PACU. • The duct enclosure was completed. • New windows were installed at E.D. Waiting. • Demolition started at Acute Care on the 2nd floor.
Work Completed This Week - 4/26/09 • ED Ambulance Entry was opened. • Wall framing and MEP install continued at PACU. • Demolition was completed at Endoscopy. • A BRB was installed at Endoscopy. • Demolition started at the Housekeeping Room near Sterile Supply.
Work Completed This Week - 4/12/09 • The Mammoth unit was removed and AHU/EF-2 was hooked up. • Demolition at PACU South and Decontam/Sterile processing was completed. • Rock was installed at the 2nd floor low roof. • Demolition continued at Respiratory Therapy. • One of the new BRB’s was installed.
Work Completed This Week - 3/29/09 • Art lanterns were installed at the lobby. • Final changes and punch list work continues at the addition. • Auto doors were installed at the ED remodels. • ILSM work has started for the next phases of the remodel. • Demolition has started at the old entrance.
Work Completed This Week - 3/1/09 • Punch list work continues throughout the addition. • Casework installation continues throughout the 1st and 2nd floors. • Carpet installation at the first floor is complete. • Wood paneling at the Lobby has been completed. • Cubicle curtains and window covering installation has started.
Work Completed This Week - 2/15/09 • The May Street stairs handrail was installed. • The glass was placed at the entrance canopy. • Installation of the tile at the main lobby was completed. • Finishes and casework are being installed throughout the 1st and 2nd floors. • Wall protection has been installed throughout the 1st floor.
Work Completed This Week - 2/08/09 • Landscaping continues around the addition. • Glass canopy installation has started. • Installation of the sunshade system has started. • Ceiling tile has been installed throughout the first and second floors. • Taping is nearly complete at the Chapel.
Work Completed This Week - 1/25/09 • Curtain wall system at the Gift Shop/Chapel is nearly complete. • Flooring in Same Day is complete and flooring at the Family Birth Center has started. • Site concrete around the addition is complete and the snow melt system is operational. • Ceiling grid has been installed at the atrium/lobby. • AHU/EF – 3 has been started.
Work Completed This Week - 1/18/09 • 2nd Floor curtain wall system and metal panels above are complete. • Flooring in the Same Day Surgery corridors has started. • The last of the snow melt system has been installed. • Drywall taping has started throughout the atrium & lobby areas. • Painting throughout the 2nd floor has started.
Work Completed This Week - 1/11/09 • A portion of the May Street stairs was poured. • Metal panels have been completed. • Windows are 90% complete. • The southwest areas of the 1st and 2nd floors have drywall installed. • Temporary occupancy has been obtained for the CUP.
Work Completed This Week - 12/7/08 • Concrete sidewalks were poured at the west alcove and the east stairs. • Metal panel installation started on the south elevation. • Curtain wall glass was installed at the 2nd floor. • Flooring and casework installation continued in the lower level. • Taping at the 2nd floor has started.
Work Completed This Week - 11/30/08 • Concrete sidewalk was poured at the north side of the addition. • Snowmelt installation and forms were completed at the east stair. • Curtain wall installation continues at the 2nd floor. • Flooring and casework installation has started in the lower level. • Drywall at the 2nd floor has started.
Work Completed This Week - 11/23/08 • The MRI magnet has been installed. • Glass block was installed at the MRI window. • Curtain wall installation has started at the 2nd floor. • Ceiling grid install started at the north portion of the 1st floor. • Sidewalk prep and snowmelt installation has started around the addition.
Work Completed This Week - 11/16/08 • Metal panels have been installed on the east & west elevations. • Stone veneer work is complete on the addition and stairs. • Casework has been installed in the MRI room. • Church Lot parking has been completed. • Drywall continues first floor & framing continues on the second floor.
Work Completed This Week - 11/9/08 • Metal panels have been installed on the north elevation. • Stone veneer work on addition is complete. Work has started on May St. stairs • Water feature concrete is complete. Stone work will follow. • Church lot walls and fine grading are ready for pavement. • Drywall and taping continues on the 1st Floor.
Work Completed This Week - 11/2/08 • The east and south lots at the addition have been paved. • Stone veneer work on the south elevation continues. • Installation of the water feature continues. • Retaining walls and excavation have been completed. • Finishes have been installed in ED West remodel.
Work Completed This Week - 10/26/08 • Curbs and fine grading completed at the Addition Lots. • Stone veneer work on the south elevation continues. • Installation of the water feature continues. • Excavation and retaining wall construction has started at the Church Lot. • Steel entrance canopy has been erected.
Work Completed This Week - 10/19/08 • Curb work at the South Lot was completed. • Stone veneer work on the south elevation continues. • Installation of the water feature continues. • The new approach and sidewalk was poured along 12th St. • Drywall hanging and taping continues on the 1st Floor.
Work Completed This Week - 10/12/08 • Curb prep. at the Addition Parking Lot has started. • Stone veneer work on the south elevation continues. • Installation of the water feature has started. • The HVAC units have been installed on the roof. • Drywall installation has started on the 1st Floor.
Work Completed This Week - 10/5/08 • Grading at Addition parking lot continues. • Stone veneer is being installed near the water feature. • The crash wall at the east stair has been poured. • Installation of the weather barrier continues. • Sidewalks and curbs have been poured along 12th and May Street.
Work Completed This Week - 9/28/08 • Grading at Addition parking lot continues. • Stone veneer has been installed on the CMU wall near the main entrance. • The retaining wall at the May St. stairs has been poured. • Installation of the weather barrier and furring at the metal panels has started. • Installation of drywall in the lower level has started.
Work Completed This Week - 9/21/08 • Grading at the Church Lot continues. • Framing of the main entrance was completed. • Wall forming has started for the May St. stairs. • RF shielding at the MRI Room was completed. • Electrical equipment testing has started.
Work Completed This Week - 9/14/08 • Exterior stud framing continues. • Clearing of the Church Lot has started. • Footings were poured for the May St. stairs. • EIFS patching was completed at the Lab BRB. • Concrete was poured at the CUP stair pans.
Work Completed This Week - 9/7/08 • Exterior stud framing continues. • The final storm line was completed. • Interior framing and MEP work continues. • BRB has been installed at near the Sleep Lab. • Mechanical install at the CUP continues.
Work Completed This Week - 8/31/08 • Exterior stud framing continues. • Exterior gyp. board is being installed. • Interior framing and MEP work continues. • BRB work has started near the Sleep Lab. • Mechanical install at the CUP continues.
Work Completed This Week - 8/24/08 • Exterior stud framing continues. • May Street retaining wall and backfill was completed. • Interior framing and MEP work continues. • BRB was installed at the Lab from the exterior. • Mechanical install at the CUP continues.
Work Completed This Week - 8/17/08 • Exterior stud framing continues. • May Street retaining wall work has started. • Interior framing and MEP work continues. • Louvers on the west side of the CUP have been installed. • Mechanical install at the CUP continues.
Work Completed This Week - 8/10/08 • Pipe installation has started at the utility shaft. • Roofing continues at the addition. • Exterior stud framing has started at the north side. • Stair installation at the CUP continues. • Perimeter curbs have been poured.
Work Completed This Week - 7/27/08 • Cooling towers were installed at the CUP. • Parapet framing was installed at the roof. • Existing braces were replaced with BRB’s. • Fireproofing of the steel continues. • The 1st floor SOG was poured.
Work Completed This Week - 7/20/08 • 2nd floor slab south of J line was poured. • The church was demolished. • Mechanical installation continues at the CUP. • Fireproofing of the steel continues. • The 1st floor SOG was prepared for concrete.
Work Completed This Week - 7/6/08 • Roof slab north of H line was poured. • Steel erection continues. • Mechanical installation continues at the CUP. • Fireproofing of the steel at the 1st Floor has started. • Interior remodel work for ASI-51 continues.
Work Completed This Week - 6/29/08 • 2nd floor of the addition north of J line was poured. • Steel erection continues. • HVAC platforms were erected on the existing hospital. • Fireproofing of the steel at the lower level was completed. • Interior remodel work for ASI-51 has started.
Work Completed This Week - 6/22/08 • Concrete approach at 12th Street was completed. • Steel erection continues. • South entrance to Dethman was completed. • Roof top AHU's were installed at the CUP. • Stairs to the NW parking lot were completed.
Work Completed This Week - 6/15/08 • New washing machine installation was completed. • Steel erection continues. • 1st floor slab on metal deck was poured. • ED Drive paving was completed. • Stairs to the NW parking lot were demolished.
Work Completed This Week - 6/8/08 • MEP in the CUP continues. • Steel erection continues. • Loading Dock modifications continue. • Curbs were installed along ED Drive. • Remodel work continued in the Emergency Department.
Work Completed This Week - 5/25/08 • MEP in the CUP continues. • Steel erection continues. • Sidewalks along Prospect were poured. • Protective enclosure was built around the exterior pipes near the ED. • Remodel work continued in the Emergency Department.
Work Completed This Week - 5/18/08 • Paving at the CUP, Park & Prospect Lot, and Park & Prospect Steets. • Steel erection continues. • Roofing at the CUP continued. • Equipment pads at the CUP were formed and poured. • Final grading a curb work was completed east of the CUP.
Work Completed This Week - 5/11/08 • Landscaping continued at the Park & Prospect Lot. • Structural steel and BRB braces arrived. • Roofing at the CUP continued. • Demolition of the existing skin. • The rebuilding of Prospect St. started.
Work Completed This Week - 5/4/08 • Landscaping continued at the Park & Prospect Lot. • MEP work continued in the tunnel and the CUP. • The CUP SOG was poured. • Slab prep at the lower addition was completed. • The footings at the upper addition were formed.
Work Completed This Week - 4/13/08 • Interior column footings were poured at the lower addition. • Curb work continued at the Park & Prospect parking lot. • Under slab MEP work started at the lower addition. • The second floor slab was poured at the CUP. • Landscape sprinkler system is being installed/repaired throughout the site.
Work Completed This Week - 4/6/08 • Grade beam at the ’57 building was poured. • Wall forms were stripped and placed for the next pour. • Waterproofing and footing drains were installed at the /57 building and the addition. • Spread footings at the lower level of the addition were formed. • Steel erection at the CUP continued.
Work Completed This Week - 3/30/08 • A dry well was discovered and was pumped and removed. • Wall forms were stripped and placed for the next pour. • Waterproofing and footing drains were installed at the /57 building and the addition. • New storefront doors were installed at the Imaging entrance. • Steel erection at the CUP continued.
Work Completed This Week - 3/23/08 • Foundation walls were poured for the addition. • Wall forms were stripped and placed for the next pour. • Curbs and sidewalks were poured around ED Drive. • Demolition and clean-up continued at the upper addition area. • Concrete slab was poured at the Electrical Building.
Work Completed This Week - 3/16/08 • First foundation walls were poured for the addition. • Wall forms were stripped and placed for the next pour. • Grading and curb work continued throughout the site. • Demolition and clean-up continued at the upper addition area. • Concrete slab over the fuel tank was poured.